Inside this Project
This project included over 5,500 linear feet of excavation and backfill for ductbanks, electric rooms, and vaults to support the new Terminal 3 Central Headhouse. Power One’s work provided essential infrastructure for concourse feeders, telecom backbone, incoming DWP power, fueling systems, and associated grounding. Excavations reached depths of up to 20 feet, requiring meticulous planning and safety measures to protect workers and ongoing airport operations.
Project Details
- 11,500+ labor hours delivered on a fast-tracked schedule
- Excavations as deep as 20 feet across sensitive airside environments
- Installation of critical underground utility systems supporting LAX modernization
- Completed in 2021 with a total budget of $3.3 million