10,000+

Hours

2024 - 2025

Date

7,000

Linear Feet of Trenching

$2,500,000

Budget

Inside this Project

Power One completed over 7,000 linear feet of trenching to support new underground electric, telecom, and security systems for Universal Studios. This complex project required precise coordination across multiple trades to ensure safe installation while maintaining access to active areas of the site.

Project Details

  • 10,000+ labor hours dedicated to successful completion
  • Extensive trenching across challenging site conditions
  • Installation of critical utility systems supporting future park infrastructure
  • Project timeline spanning 2024–2025 with a budget of $2.5 million